Incremental Model (2017)
CSS CS Optional — Paper-I, Section-B, Topic V.
🔑 Definition
- System built as series of increments/"builds" — each adds functional capability.
- First increment = core product with basic requirements.
📌 How Each Increment Runs
- Mini-Waterfall per increment: analysis → design → code → test → deliver, repeated.
📌 Advantages
- Fast working software
- Early increments = usable, testable products
- Cheaper to accommodate scope changes
- Easier to test/debug (smaller pieces)
- Customer feedback on one increment steers the next
📌 Disadvantages
- Needs solid upfront planning + well-defined architecture
- Total cost can exceed Waterfall if increments aren't planned well
⚠️ MCQ Trap
- Incremental = complete, working slices added one after another.
- Evolutionary = keeps refining ONE evolving version.
📜 Past-Paper Questions & MCQs (CSS 2016–2026)
2018 · Paper-I · Q7(d) · 4 marks
Q. What type of project is not suited to incremental methods?
Ans.
- Small projects with few features, where splitting into increments only adds overhead.
- Projects with fixed, complete requirements and one final delivery, where waterfall is simpler.
- Systems that cannot be divided into independent parts, such as tightly integrated embedded or real-time control systems.
- Safety-critical systems (aircraft control, medical devices) that need a complete specification and full verification before any release.
- Projects with no stable overall architecture at the start, because later increments may force costly redesign.
Related
- The 2017 Q4(a) answer on choosing evolutionary versus incremental models is on Evolutionary Model (2017).